Skip to main content

Neilson Library Construction Update, August 7, 2018

New Neilson

Published August 7, 2018

There will be another, but smaller concrete pour this Friday. It will require a concrete pumper and deliveries by 16 concrete trucks to the construction site at the back side of Hatfield Hall. Work will start at 7 a.m. and complete before noon.

Also, next week the electrical contractor will be pulling and terminating new medium voltage electrical feeders for Neilson Library at two vaults outside of the construction area between Wright Hall and Sabin Reed near the Lanning Fountain, and at the east side of Bass Hall. Work will begin on Tuesday, August 14 and complete on Wednesday. There will NOT be power interruptions related to this work and the work will create little noise or disruption.

Contact

Charlie Conant 
Project Manager
Facilities Management
413-585-2424
cconant@smith.edu

Peter Gagnon
Capital Construction Director
Facilities Management
413-585-2406
pgagnon@smith.edu

Roger Mosier
Associate Vice President
Facilities Management
413-585-2400
rmosier@smith.edu